Road Reseal Works Coming Up
Fulton Hogan has been awarded the contract for the Kaikoura reseal programme.
Works will be starting after Waitangi Weekend on the 10th of February.
Below is the programme of works:
9th February: Site establishment
10th February: Cromer Street and Austin Street
11th - 13th February: Esplanade
14th February: Yarmouth Street
14th - 17th February: Ludstone Road
17th February: Hawthorne Road
Please note that these dates are subject to change due to weather conditions.
During these dates, please expect delays and drive safely during this period.
If you have any questions or concerns relating to this work, please contact us on the numbers provided below.
Steven Murray, Contract Manager – 027 702 7972
Luke Webley, Contract Supervisor – 027 886 0807
Terry McIntosh , Site Traffic Management Supervisor – 027 707 8926